Dates are moved a big amount of years after particular actions on Gantt module

    XMLWordPrintable

Details

    • Yes
    • Tree
    • BigPicture, BigGantt
    • JIRA server
    • 5
    • 5
    • $i18n.getText("admin.common.words.hide")
      $i18n.getText("admin.common.words.show")
      var cfToHide1 = document.getElementById("rowForcustomfield_18501"); if(cfToHide1){cfToHide1.style.display="none";} var cfToHide2 = document.getElementById("rowForcustomfield_18502"); if(cfToHide2){cfToHide2.style.display="none";} var cfToHide3 = document.getElementById("rowForcustomfield_19700"); if(cfToHide3){cfToHide3.style.display="none";} var cfToHide4 = document.getElementById("rowForcustomfield_18400"); if(cfToHide4){cfToHide4.style.display="none";}
    • Sprint 2020/28, Sprint 2021/01, Sprint 2021/02, Sprint 2021/03 SIW, Sprint 2021/04
    • PI2021/2
    • 2 weeks, 4 days, 6 hours, 56 minutes, 11 seconds
    • 6 hours, 11 minutes, 15 seconds
    • 1 week, 4 days, 16 hours, 30 minutes, 30 seconds
    • 18 hours, 25 minutes, 51 seconds
    • 1 hour, 7 minutes, 35 seconds
    • 3 days, 22 hours, 30 minutes, 1 second
    • 1 week, 5 days, 1 hour, 42 minutes, 13 seconds

    Description

      Prerequisites:

      • Create new project with 5 issues
      • Change status of issue 1 and issue 2 to "In progress"
      • Go to search issue page in Jira and create filter (based on status) that includes only two issues in status "In progress"
      • Go to Overview and create 2 new boxes.
      • In first box add to scope created project, in second box add created filter.
      • Go to Gantt of first box. Create links :
        Issue 2 -> Issue 4 (End to start)
        Issue 2 -> Issue 5 (End to start)
        Issue 3 -> Issue 2 (End to start) - to see how structure should look like see screenshot attached.

      Reproduction steps: for full video with reproduction steps attached

      • Go to second box (with filter added in scope)
      • Indent issue one under issue 2 - see screenshot
      • Go to first box and create link between issue one and issue 3 (End to start) - if link is created perform below steps:
      • Delete link
      • Go to Jira issue view of issue 1 and issue 2 and change status to any other than "in progress" 
      • Go back to Gantt of second box and do page refresh - no issues inside box after page refresh
      • Go back to Jira issue view of previously edited issues and change their status again to "in progress"
      • Go back to Gantt of second box and do resync
      • Indent issue 1 under issue 2
      • Go to Gantt module of first box (based on project) and link Issue 1 with issue 3 with End to Start link.

      Actual result:
      Issue is not created correctly. Issues are moved a big amount of years forward. 

      Expected result:
      Link is not created because it's causing circular relation. Tasks are not moved forward a couple of years. 
      Workaround:
      N/A

      Attachments

        Activity

          People

            pawel.wesolowski Pawel Wesolowski
            katarzyna.rajchert Katarzyna Rajchert
            jakub.zygmunt Jakub Zygmunt , system.jenkins Jenkins , system.gerrit Gerrit , igor.szymanczyk Igor Szymanczyk , jerzy.sekula Jerzy Sekula , kamil.harasimiuk Kamil Harasimiuk , pawel.guz Pawel Guz , radoslaw.rachuba Radosław Rachuba , martyna.turowska Martyna Turowska , katarzyna.rajchert Katarzyna Rajchert
            Votes:
            0 Vote for this issue
            Watchers:
            2 Start watching this issue

            Dates

              Created:
              Updated:
              Resolved: