Artificial tasks are moved one day to the past when PC's time zone is later than the server's [MYSQL Database]

    XMLWordPrintable

    Details

    • Team:
      Tree
    • Product:
      BigPicture, BigGantt
    • Host platform:
      JIRA server, JIRA cloud
    • Customer Rank:
      5
    • Hide Fields:
      $i18n.getText("admin.common.words.hide")
      $i18n.getText("admin.common.words.show")
      var cfToHide1 = document.getElementById("rowForcustomfield_18501"); if(cfToHide1){cfToHide1.style.display="none";} var cfToHide2 = document.getElementById("rowForcustomfield_18502"); if(cfToHide2){cfToHide2.style.display="none";} var cfToHide3 = document.getElementById("rowForcustomfield_19700"); if(cfToHide3){cfToHide3.style.display="none";} var cfToHide4 = document.getElementById("rowForcustomfield_18400"); if(cfToHide4){cfToHide4.style.display="none";}
    • Sprint:
      Sprint 2019/11, Sprint 2019/12, Sprint 2019/13, Sprint 2019/14
    • Time in "OPEN":
      61 weeks, 3 days, 22 hours, 35 minutes, 10 seconds
    • Time "In Progress":
      0
    • Time "In Review":
      0
    • Time "In QA Review":
      0
    • Time "In Test Scenario Review":
      0
    • Time "Waiting for Merge":
      0
    • Time "Waiting for Release":
      0

      Description

      Prerequisities: 

      Prepare instance with clean mysql database
      **

      • The issue also occurs on Cloud, but it is impossible to check server's time zone there (although it is suspected to be UTC+0)
      • Time zone is affected by DST

      Reproduction steps (for Server apps):

      1. Open Jira and navigate to Jira administration -> System -> System info
      2. Note the server's time zone set in System Time
      3. Set your PC's time zone to earlier than or equal to the server's: for example GTM +1 [Warsaw]
      4. Open any Program in BigPicture/BigGantt
      5. Proceed to Gantt module
      6. Create a new artificial task with any date
      7. Set your PC's time zone to later than server's: for example GTM -3 [Brasil]
      8. Create another artificial task with any date
      9. Change duration of second artifial task to one day longer or one day shorter

      Actual result:
      The second artificial task after resizing/shortening is moved one day to the past.

      Expected result:
      Both artificial tasks are created on the selected days.

      Workaround
      N/A

        Attachments

          Issue Links

            Activity

              People

              Assignee:
              Unassigned Unassigned
              Reporter:
              piotr.romanski Piotr Romański (Inactive)
              SoftwarePlant People involved:
              grzegorz.duzy Grzegorz Duży , sebastian.janda Sebastian Janda , katarzyna.rajchert Katarzyna Rajchert , igor.szymanczyk Igor Szymanczyk , mateusz.kielbowicz Mateusz Kielbowicz , evgeny.frolov Evgeny Frolov (Inactive) , bartosz.radomski Bartosz Radomski (Inactive) , michal.niwinski Michal Niwinski , kamil.wasikowski Kamil Wasikowski (Inactive) , pawel.guz Pawel Guz , jerzy.sekula Jerzy Sekula , lukasz.pawelczak Łukasz Pawełczak , piotr.romanski Piotr Romański (Inactive)
              Votes:
              0 Vote for this issue
              Watchers:
              4 Start watching this issue

                Dates

                Created:
                Updated:
                Resolved: